Extension programme for Frankfurt Airport as a business hub – new access roads
Frankfurt Airport (Fraport) is the largest airport in Germany and the fourth largest in Europe in terms of traffic volume. Fraport AG is planning to further increase passenger handling capacity at Frankfurt Airport. In addition to the existing buildings in the north, Terminals 1 and 2, the new Terminal 3 is being built in the south of Frankfurt Airport on the site of the former US airbase (now CargoCity South). The overall measure includes the South Expansion Area and Terminal 3. As a result of this measure, extensive adaptation measures and reorganisation of the airport’s development will be necessary.
This primarily includes the traffic development south-east with a new construction of 18.5 ha of traffic facilities and various bridge structures with the aim of connecting the new Terminal 3 as well as CargoCity South (CCS) and all service roads in this area to the public transport network via the existing junction on the BAB 5 motorway. In addition, the supply and disposal facilities, including 9.7 km of DN 150 – DN 1600 wastewater and rainwater sewers, 5.0 km of 8×8 KSR cable conduit routes and two wastewater pumping stations with a capacity of 50 l/s were newly designed or extensively adapted in this area. Due to the different security areas at the airport, a total of five gate systems including the necessary control buildings were designed. Construction roads and fallow land were continuously designed or re-designed, e.g. for car parks or storage areas.
A particular challenge is the realisation of the entire project under the flowing traffic of the major construction site of Terminal 3 and the CCS. As part of the design process, KOCKS ENGINEERS intensively investigated the future traffic relationships, including those during the construction period, and incorporated this into the various options for traffic development as well as into an overarching realisation concept for a smooth construction process. Traffic routing concepts as well as necessary provisional arrangements and temporary gate systems were continuously coordinated and adapted with the third parties involved.
Coordination with numerous internal project interfaces as well as the interfaces to third-party measures and other parties involved with the client, such as construction logistics and ground management, were necessary to ensure that the project ran smoothly. In particular, the requirements for the absence of explosive ordnance and the consideration of existing soil contamination (PFC) in the area of a former military base must be emphasised here.
In addition to the technical supervision of the construction project, all of these interfaces must continue to be monitored during construction and, in the event of changes to the construction process, possible measures must be developed to counteract conflicts while maintaining quality, costs and deadlines, and the project process must be adapted with the involvement of potential stakeholders.
Building Information Modelling (BIM) in transport infrastructure
In order to set up a project for the future in accordance with the BIM masterplan for federal trunk road construction, the BIM methodology must be implemented in the design process right from the start. This modern design method ensures the quality of the design results and avoids duplication of work.
KOCKS ENGINEERS have been working for almost two decades on the topic of how added value can be created from 3D model generation for our own machining process and thus also for our customers. The following applications regularly emerge:
- Checking clearances
- Checking stopping sight distances
- Collision checking
- Quantity determination
- Integration of subsoil horizons and seals
- Visualisation
- Transfer of 3D model content to 2D plans, avoidance of transfer errors
- Linking traffic system – immission control – civil engineering
Model-based design has advantages over conventional processing, especially when the planning results of different specialist planners have to be coordinated at an early design stage. In the major project ‘Eight-lane expansion of the A 1 motorway between the Cologne-Niehl interchange and the Leverkusen-West interchange, including the Leverkusen Rhine bridge’, which was under particular public pressure, the models helped to effectively and efficiently design the coordination process between roads, civil engineering and landfill construction.
In the project ‘Reconstruction of the Charlottenburg motorway junction and the replacement of the Rudolf-Wissell-Bridge’, the conditions for model-based approval are being created. To this end, KOCKS ENGINEERS have developed a modelling method with which the results of the noise investigation can be entered into a coordination model as a partial model. The result display of the partial model corresponds to the level result lists suitable for design approval.
Since 2023, KOCKS ENGINEERS have been preparing the road design for the six-lane expansion of the A 3 motorway between the Nittendorf junction and the Regensburg interchange. In this project, all the formalities of BIM design (AIA, BAP, attribution, model creation and model checking) are already being used in the preliminary design phase.
Measures for climate change adapted urban development in Barisal (Bangladesh), Phase I
The project is financed by KfW as part of the German financial cooperation with the Government of Bangladesh and implemented by the Barishal City Corporation. The joint venture between Kocks Consult GmbH, Germany, and BCL Ltd, Bangladesh, was commissioned by KfW on behalf of BCC to implement the project, which aims to alleviate flooding in the city, particularly in the central neighbourhoods and slum areas.
The city of Barishal, with an area of 58 m², is located on the banks of the Kirtankhola River in south-central Bangladesh, 106 km north of the Bay of Bengal. At only 1 m above sea level, the city is at high risk of flooding and cyclones, with the western parts of the city and its residents and businesses suffering the most damage. The overall goal of the project is to reduce vulnerability and strengthen adaptive capacity to the challenges of climate change, especially for the vulnerable populations in the city.
To achieve the project objectives, the following measures will be implemented:
- Climate change adaptation measures,
- Comprehensive flood mitigation measures.
The following components were selected for the first project phase:
- New construction and partial enlargement of stormwater sewers with a length of 22.7 km. Hydrodynamic sewer network calculations taking into account tidal influences of up to 1 m in Barishal;
- Renewal and raising of low-lying roads over a length of 2.8 km;
- Deepening and dredging of the Sagardi canal to increase the storage volume of the existing water bodies over a length of 7.1 km and construction of cycle paths and footpaths along the canal, including a new footbridge;
- Raising the land in the low-lying area of Kala Potty Slum and improving the basic infrastructure (water supply, drainage and paths). Involvement of the residents of the area through community contracting for the flood-related structural elevation or new construction of the houses.
Extension of the Opel Szentgotthárd Ltd. production site, Hungary
KOCKS ENGINEERS support the development of industrial sites, their expansion and conversion, modernisation and dismantling with a particular focus on the automotive, glass, building materials and mechanical engineering sectors.
Starting with urban land-use planning, we offer our clients the entire spectrum of development planning for their site and property and structural planning for projected site expansions, including the necessary technical building services and electrical planning. Construction and site supervision, health and safety coordination and project management services round off this spectrum.
At the Opel site in Szentgotthárd (Hungary), KOCKS ENGINEERS were awarded the contract for project management, general design and construction supervision for the new construction of an engine plant, including structural alterations to the existing buildings. The conversion and new construction resulted in a contiguous production area of around 60,000 m² for the new engine production. After completion of the buildings, KOCKS ENGINEERS finally coordinated the machine delivery, installation and commissioning. The project also included health and safety coordination and the expansion of the infrastructure for energy and media supply as well as upgrading the internal roads, including the factory railway.
Major projects like this laid the foundation for the successful diversification of the customer base into other industrial sectors. Today, KOCKS ENGINEERS support its customers in areas such as:
- The creation of a legal planning basis for the construction of new production halls, material warehouses and storage areas in the building materials industry.
- The refurbishment and conversion of production buildings for container glass, including the construction of new filter systems with chimneys.
- The media separation of production areas while maintaining the supply to neighbouring or media-connected buildings in the automotive industry.
- The expansion and modernisation of production areas during ongoing operations.
- The conversion of engine test benches with battery and fuel cell technology.
- The new construction and conversion of industrial buildings in steel, timber and solid construction for the production of aluminium beverage cans.
- Health and safety coordination on major construction sites in the automotive, chemical, glass and beverage industries, as well as road, water and transport construction sites.
Waste Management Maldives
Based on a feasibility study prepared by KOCKS ENGINEERS in 2017, the Asian Development Bank (ADB) has approved funding of 140 million US dollars to improve waste management in the Maldives. Phase 1, with a volume of USD 40 million, will initially focus on improving waste logistics (collection, transport, transfer, pre-treatment) in the greater Male’ area. In phase 2, a waste incineration plant is to be built and operated as a DBO (Design-Build and Operate) in accordance with international standards.
KOCKS ENGINEERS and their local partner Water Solutions were then commissioned by the Maldivian Ministry of Environment for the catchment area of the capital Malé (Male‘, Hulhumale’, Velana airport island, Vilimale’, Gulifalhu and Thilafushi industrial islands) as well as the northern, southern and western atolls around the capital, and western atolls around the capital with measures to develop a collection and transport system, the design and construction supervision of several transfer stations and the reorganisation of the waste recycling island of Thilafushi, located 10 km off Malé (phase 1 from 2019 to 2023).
In 2021, suitable engineering measures were taken to extinguish the landfill fire on Thilafushi, the smoke from which had previously severely affected the population of the capital Malé and the tourism industry. At the same time, a new 900 m long jetty, a 30,000 m² concrete operating area and various operating and workshop buildings were constructed. The employees of the waste management company were comprehensively instructed and trained in the use of the new facility and the overall waste management concept for Malé.
On Malé and the neighbouring island of Vilimale’, the design, tendering and construction supervision of waste transfer stations and associated infrastructure measures were implemented. In addition, the entire procurement of the technically required infrastructure (collection and transfer containers, vehicles, ships) with a total volume of 10 million US dollars was implemented and supervised by KOCKS ENGINEERS and Water Solutions.
The centrepiece of the waste management system on the main island of Malé is a two-storey waste transfer station, where both municipal waste vehicles and small private suppliers can dispose of their waste. The transfer station was dimensioned for a waste volume of approx. 500 tonnes per day (approx. 70 % household waste/household waste-like, approx. 30 % building rubble/construction waste). After pre-compaction, a container-based transfer by ship to Thilafushi takes place. The separately collected recyclable materials such as plastic, paper and cardboard are then baled and temporarily stored on Thilafushi.
On the island of Vandhoo in Raa Atoll, in the north of the country, KOCKS ENGINEERS and Water Solutions established a smaller pilot plant for a waste-to-energy facility (World Bank project) between 2012 and 2015.
The waste management system of the main region is urgently awaiting the completion of a corresponding large-scale plant on Thilafushi, which the ADB is implementing in the second phase of the project.
KOCKS ENGINEERS have been active in the waste management sector in the Maldives for more than 10 years now. Through the long-standing partnership with Water Solutions and the trustful cooperation with the Ministry of Environment as a client, KOCKS ENGINEERS have been able to continuously follow and shape the development of the Maldives towards an integrated and developed waste management system.
A feasibility study carried out by KOCKS ENGINEERS and financed by IRENA (International Renewable Energy Agency/Abu Dhabi Fund) at three locations in the country in 2016 and a feasibility study with preliminary design as part of the EU’s Climate Change Adaptation Programme in Addu City in the south (2015-2016) have also led to the financing of further infrastructure measures to improve waste management. In parallel to the 2017 feasibility study in Greater Male‘, the Ministry commissioned KOCKS ENGINEERS to draw up the conceptual planning for the closure of the Thilafushi landfill and the transfer stations in Male’, Hulumale‘ and Vilimale’.
Extension programme for Frankfurt Airport as a business hub – new access roads
Frankfurt Airport (Fraport) is the largest airport in Germany and the fourth largest in Europe in terms of traffic volume. Fraport AG is planning to further increase passenger handling capacity at Frankfurt Airport. In addition to the existing buildings in the north, Terminals 1 and 2, the new Terminal 3 is being built in the south of Frankfurt Airport on the site of the former US airbase (now CargoCity South). The overall measure includes the South Expansion Area and Terminal 3. As a result of this measure, extensive adaptation measures and reorganisation of the airport’s development will be necessary.
This primarily includes the traffic development south-east with a new construction of 18.5 ha of roads and various bridge structures with the aim of connecting the new Terminal 3 as well as CargoCity South (CCS) and all service roads in this area to the public transport network via the existing junction on the BAB 5 motorway. In addition, the supply and disposal facilities, including 9.7 km of DN 150 – DN 1600 wastewater and rainwater sewers, 5.0 km of 8×8 KSR cable conduit routes and two wastewater pumping stations with a capacity of 50 l/s were newly designed or extensively adapted in this area. Due to the different security areas at the airport, a total of five gate systems including the necessary control buildings were designed. Construction roads and fallow land were continuously designed or re-designed, e. g. for car parks or storage areas.
A particular challenge is the realisation of the entire project under the flowing traffic of the major construction site of Terminal 3 and the CCS. As part of the design process, KOCKS ENGINEERS intensively investigated the future traffic relationships, including those during the construction period, and incorporated this into the various options for traffic development as well as into an overarching realisation concept for a smooth construction process. Traffic routing concepts as well as necessary provisional arrangements and temporary gate systems were continuously coordinated and adapted with the third parties involved.
Coordination with numerous internal project interfaces as well as the interfaces to third-party measures and other parties involved with the client, such as construction logistics and ground management, were necessary to ensure that the project ran smoothly. In particular, the requirements for the absence of explosive ordnance and the consideration of existing soil contamination (PFC) in the area of a former military base must be emphasised here.
In addition to the technical supervision of the construction project, all of these interfaces must continue to be monitored during construction and, in the event of changes to the construction process, possible measures must be developed to counteract conflicts while maintaining quality, costs and deadlines, and the project process must be adapted with the involvement of potential stakeholders.
Construction of a new district heating pipe in Frankfurt
Netzdienste Rhein-Main GmbH (NRM), a wholly owned subsidiary of Mainova AG, planned the construction of a DN 500 district heating connection pipeline with a total length of 3.2 km, starting from the Niederrad network, continuing through a newly constructed culvert under the river Main to the West CHP plant and from there to the CHP plant at the Frankfurt trade fair. By networking the combined heat and power plants, they can be utilised more efficiently and flexibly, which leads to increased efficiency of the district heating network and enables greater use of carbon-neutral heat from the Nordweststadt waste-to-energy plant, which is also connected. Overall, this has led to considerable savings in CO² emissions.
KOCKS ENGINEERS’ task was to plan the engineering structures and technical equipment, to prepare the structural design of the culvert structures, to carry out the preliminary EIA assessment and the construction supervision.
In order to connect the Niederrad CHP plant with the West CHP plant and from there to the CHP plant at the trade fair, the district heating route had to overcome some special challenges. One section of the route ran under the river Main and another under the railway apron of Frankfurt Central Station, where 32 tracks had to be crossed. In other sections, the route was laid partly above ground as an overhead line and partly underground.
In order to lay the lines under the Main and the track apron, supply tunnels were built at a depth of 6 m under the track apron and 10 m under the riverbed of the Main; these tunnels had a diameter of 2.50 m. Mechanised tunnelling methods were used to lay the underground lines.
A very extensive monitoring programme was required for the crossing of the 32 tracks of the track apron of Frankfurt Central Station; all tracks were continuously surveyed using automatic total stations. During the entire construction project, four tachymeters checked measuring points placed at the sleepers in all three coordinate directions at regular 20-minute intervals. The recorded data was made available in real time via an internet-based platform that could be permanently viewed by all those involved.
In addition to the underground culvert structures, pipe bridges were also required to cross roads and railway tracks. The acceptance of the prefabricated steel components was carried out by a welding engineer from KOCKS ENGINEERS on site at the plant in Poland.
Eight-lane widening of the federal motorway A 1 and construction of a new Rhine bridge in Leverkusen
In 2012, it was discovered that the Leverkusen Rhine bridge, which dates back to the 1960s, had serious structural damage. The need to close the motorway to trucks weighing more than 3.5 tonnes on several occasions since 2013 due to the structural damage led to high economic and private losses.
At the beginning of 2013, Straßen.NRW invited four engineering firms specialising in large bridge construction to take part in a two-stage ideas competition. In this competition, the group led by the engineering firm GRASSL, in which KOCKS ENGINEERS are responsible for the roads, drainage design and the technical noise report, was able to prevail against strong competition.
The construction project to be planned comprises the new construction of the Rhine bridge and the expansion of the A 1 motorway and covers the area from the Cologne-Niehl junction (inclusive) to the Leverkusen-West motorway junction, including the so-called ‘elevated road A’. The section of the A 1 motorway will be widened to eight continuous lanes due to the forecast future traffic volumes. An additional manoeuvring lane in each direction will be provided between the Cologne-Niehl junction and the Leverkusen-West interchange. The ramp alignment at the Leverkusen-West motorway interchange will be adapted to the modified route of the A 1 motorway.
Intensive consultations were carried out with regard to the ability to obtain design permission and the feasibility of construction, including the proportionality of noise protection systems, construction procedures in the old landfill, replacement routes for pipelines, new and modified discharges into water bodies, flood protection and diversion routes for various construction phases.
For the design approval, the design documents were prepared, the synopses for the objections were drawn up, the one-week hearing was accompanied and the company was involved in the proceedings at the Federal Administrative Court in Leipzig.
Due to the project environment of the old Dhünnaue landfill, complex tasks had to be solved as part of the detailed design, including the execution of the foundation and the connection of the surface sealing of the old landfill to the new structures. In addition, the aspects of a sealing wall/barrier wall running in the vicinity of the A 59 motorway had to be taken into account in the design. The five basin facilities were designed according to the Guidelines for structural measures on roads in water protection areas (RiStWaG). One basin system is planned as a retention soil filter basin.
The urgency of the project required several specialist disciplines to work in parallel. BIM-orientated processing methods ensured efficient and effective information processing.
Water supply for refugee camps and hosting communities in Dohuk, Iraq
There are several camps for refugees from Syria and other parts of Iraq in the Dohuk region. Five camps with a total of 90,000 refugees as well as local communities with 144,000 inhabitants are supplied with water from Lake Mosul thanks to the project. The project includes water extraction from Lake Mosul and a drinking water treatment plant with a capacity of 2,500 m³/h as well as an elevated tank (4 x 3,500 m³) and 20 km of DN 300 – DN 1200 transport pipes. The seasonal fluctuations of 30 m in the lake water level and the poor subsoil in the lake, which did not allow for a foundation, posed a particular challenge for the design of the pumping station in Lake Mosul. A pontoon solution with four pumps was chosen, which can be put into operation depending on the water level.
Construction of a new district heating pipe in Frankfurt
Netzdienste Rhein-Main GmbH (NRM), a wholly owned subsidiary of Mainova AG, planned the construction of a DN 500 district heating connection pipeline with a total length of 3.2 km, starting from the Niederrad network, continuing through a newly constructed culvert under the river Main to the West CHP plant and from there to the CHP plant at the Frankfurt trade fair. By networking the combined heat and power plants, they can be utilised more efficiently and flexibly, which leads to increased efficiency of the district heating network and enables greater use of carbon-neutral heat from the Nordweststadt waste-to-energy plant, which is also connected. Overall, this has led to considerable savings in CO² emissions.
KOCKS ENGINEERS’ task was to plan the engineering structures and technical equipment, to prepare the structural design of the culvert structures, to carry out the preliminary EIA assessment and the construction supervision.
In order to connect the Niederrad CHP plant with the West CHP plant and from there to the CHP plant at the trade fair, the district heating route had to overcome some special challenges. One section of the route ran under the river Main and another under the railway apron of Frankfurt Central Station, where 32 tracks had to be crossed. In other sections, the route was laid partly above ground as an overhead line and partly underground.
In order to lay the lines under the Main and the track apron, supply tunnels were built at a depth of 6 m under the track apron and 10 m under the riverbed of the Main; these tunnels had a diameter of 2.50 m. Mechanised tunnelling methods were used to lay the underground lines.
A very extensive monitoring programme was required for the crossing of the 32 tracks of the track apron of Frankfurt Central Station; all tracks were continuously surveyed using automatic total stations. During the entire construction project, four tachymeters checked measuring points placed at the sleepers in all three coordinate directions at regular 20-minute intervals. The recorded data was made available in real time via an internet-based platform that could be permanently viewed by all those involved.
In addition to the underground culvert structures, pipe bridges were also required to cross roads and railway tracks. The acceptance of the prefabricated steel components was carried out by a welding engineer from KOCKS ENGINEERS on site at the plant in Poland.
Technical assistance for the construction of Pfaffendorf Bridge in Koblenz
The replacement construction of the Pfaffendorf Bridge has been underway since 2022. The demolition work on both bridgeheads and the preparatory work for the laterally offset new construction of the bridge are currently taking place.
Technical manuals for waste management, Algeria
Following the success of the first manual ‘Landfill Construction’ in 2017, GIZ in Algeria commissioned two more volumes in French in 2024: Volume 1 ‘Collection and Logistics in Waste Management’ and Volume 2 ‘Waste Treatment’.
Update of the feasibility study ‘Climate change-adapted urban development Barishal, Bangladesh’
Update and supplementation of the feasibility study for climate change-adapted urban development dated 2016. Definition of measures to reduce flooding and heat island effects, including by upgrading and expanding green and water areas in the urban area.
Climate Risk and Greenhouse Gas Emission Assessment Road Upgrading Tajikistan
Optimisation of an existing road design and technical specifications according to the latest requirements of the ADB ‘Green Roads Toolkit’ with a view to complying with the Paris Climate Agreement.
Maintenance of Papua New Guinea’s transport infrastructure
Creation of a database to measure changes ‘before’ and ‘after’ the implementation of IFI-funded maintenance programmes along six highways in Papua New Guinea.
Environmental and social assessment of the road extension Dangara – Guliston, Tajikistan
Extension of 49 km of road to improve the transport of goods in the region. Comprehensive environmental and social impact assessments (ESIA) are required in order to obtain co-financing from the EBRD and ADB.
Waste transfer station Malé, Maldives
Construction of a two-storey transfer station in the capital Malé. Waste volume approx. 500 tonnes per day. Can be used by municipal waste vehicles and small private deliveries. Construction of a six-storey administration building and a workshop for maintenance and repair work.
Innovative water management for the residential area “Am Aubuckel”
Interdisciplinary research project together with GBG – Mannheimer Wohnungsbaugesellschaft mbH and Technical University of Darmstadt to convert two apartment blocks into a ‘sponge city’ project with 74 residential units. The aim is to make efficient use of local water flows, including innovative rainwater management and maximum recycling of grey water for reuse. Excess service water is to supply the green areas and the old trees in the residential complex via an integrated irrigation system.
Expansion of renewable energies: Mogendorf solar park
Creation of the legal planning requirements for the construction of a ground-mounted photovoltaic plant in the local community of Mogendorf.
Hydraulic model for new bridge construction
Construction of a new bridge “Bismarckstraße” over the River Aar in Diez. For the new construction cross-section, it had to be demonstrated that the new bridge cross-section would not lead to a deterioration of the hydraulic situation in the event of flooding.
Project management Kleyerquartier / Westville
Project management for the development of a new residential area, the “Kleyerquartier / Westville” in Frankfurt/Main.
Fibre optic expansion in the city of Offenbach/Main
Expansion of the fibre optic infrastructure in the city of Offenbach with a total length of 196 km.
BIM design: Upgrading of the federal motorway section A3 Nittendorf – Regensburg
Extension to six-lanes of the A3 motorway section between the junction Nittendorf and the motorway junction Regensburg over a length of 13 km with 18 intersection structures including the 930 m long Danube bridge in Sinzing. The planning process is being optimised for the fastest possible implementation of the replacement construction of the Danube bridge.
Photovoltaic system in the vehicle hall of the Koblenz sewage treatment plant
Construction of a photovoltaic system on the vehicle hall of the Koblenz sewage treatment plant.
Renewal of the existing excess sludge centrifuges
Renewal of the two existing excess sludge centrifuges at the wastewater treatment plant Jägersfreude including flocculation station.
Renewal of a dosing station
Replacement of the existing precipitant dosing station (storage tank and dosing station in container) at the Dormagen-Rheinfeld sewage treatment plant.
Koblenz sewage treatment plant – Energy self-sufficient sewage treatment plant (SusTreat) – Sludge drying
Supply of the sewage sludge drying plant by planning a heating centre and a heating network at the Koblenz sewage treatment plant.
Telehouse pumping station
Construction of a new pumping station for pumping untreated, industrial and surface wastewater into an existing sewer.
Refurbishment of the pumping station at Bosener Mühle
Refurbishment of the pumping station at Bosener Mühle.
Supervision of technical equipment installation
Installation of technical equipment for two pumping stations on the A 57 motorway.
You need to load content from reCAPTCHA to submit the form. Please note that doing so will share data with third-party providers.
More Information