Concrete Structures

Traffic structures for the extension of the motorway B 266 between Schaven and Lohmühle

Bilder 1 Images

New construction of the Sandberg flyover with noise barrier and new construction of a rainwater retention basin as part of the traffic upgrading and four-lane expansion of the B 266 motorway between the Wißkirchen junction (motorway A 1) and the Mechernich-Roggendorf bypass. 

Client
Road construction authority of North Rhine-Westphalia / City of Mechernich
Project Manager
Dr.-Ing. Manfred Heß
Services

Design for engineering structures; structural design; road design; rainwater and wastewater drainage; landscape conservation plan; environmental report; traffic management during construction; construction supervision; pipeline coordination.

Technical Information

4-streifiger Ausbau der B 266 auf 1.900 m Länge; 1 Regenrückhaltebecken mit Regenklärbecken; 2 Stützwände; 1 Lärmschutzwand Höhe = 5,50 m , Länge = 415 m; 1 Wirtschaftswegunterführung