Power Supply
30 kV grid extension – mini-tunnel
Network extension between two existing substations by crossing a busy transport hub (including railway tracks) using a 100-metre-long DN 1300 segment-driven tunnel at a depth of 8 metres. Insertion of the pre-assembled empty conduit package into the tunnel via the launch pit once the tunnel has been completed. Final connection to the cable conduit route that has already been laid.